Skip to content
Welcome to the new Tahua Help Center!
For the complete documentation index, see llms.txt. This page is also available as Markdown.

Creating a Contract Variation

Use a Contract Variation to formally amend a signed Contract, for example to add a Milestone or change a Milestone's date or amount.

A Contract Variation is a formal amendment to a signed Contract. It's a separate Contract that sits alongside the original, signed by both parties in its own right. The original Contract stays active and unchanged, and its Milestones carry on as they are.

This means a Variation only needs to contain what's changing, not a copy of the whole Contract.

Just need to add a Milestone, and it doesn't need to be signed? You don't need a Variation. See Adding Milestones to a Live Contract.

What carries over from the original Contract

Carried over automatically (and can't be changed on the Variation)
Entered fresh on the Variation

The linked Application (if any)

Title

Contract Category

Start and end dates

Contract Manager

Contract Amount

Bank account number

Milestones

Contract document and signatories

The Counterparty starts as the original Contract's Counterparty, but you can change it on the Variation, for example if the original organisation has handed the work on to someone else. See Creating a Contract.

The original Contract's Milestones are not copied into the Variation. They stay on the original Contract, where they continue to be tracked, submitted and paid as normal.

How to create a Variation

1

Open the original Contract

Go to Contracts, open the Contract you want to vary, and click Create Variation in the Actions section of the sidebar.

Create Variation only appears on an original Contract once it's fully executed (signed by your organisation). It isn't offered on a Variation, because a Variation can't be varied further. If you need to change a Variation, create another Variation against the original Contract.

2

Details

Enter a title and the start and end dates for the Variation. The original Contract is shown at the top of the page for reference. The Counterparty is carried over from the original Contract; change it here if the Variation is with someone else.

3

Milestones

Add only the new Milestones that this Variation introduces, using Create Milestone or Import Template. You can also click Skip Milestones if the Variation doesn't add any.

You don't need to re-add the original Contract's Milestones. To change one of those, see Changing an existing Milestone below.

4

Funding

Enter the Contract Amount for this Variation.

5

Document

Choose the Contract template for the Variation, add signatories, and preview the document, or upload a document that was signed outside Tahua.

6

Send Contract

Send the Variation for signing. Once signed, it appears as its own Contract, linked to the original.

Changing an existing Milestone

To change the due date or amount of a Milestone that's already on the original Contract:

  1. Edit the Milestone where it is, on the original Contract. Open it from the original Contract and update its Due date and Amount. This keeps tracking and payment correct, and avoids having two versions of the same Milestone.

  2. Record the change in the Variation document, for example: "Milestone 2: due date changed from 31 March to 30 June; amount changed from $10,000 to $12,000."

Making the changes clear to the other party

Tahua doesn't highlight differences between the original Contract and the Variation, so it's best to spell them out. We recommend the Variation document includes a short summary of what's changed, such as Milestones added, dates or amounts changed, and any new terms.

If you'd also like the full picture in the document, these personalisations are available in your Contract template:

  • [[milestone_table]]: the Variation's own (new) Milestones

  • [[main_contract_milestone_table]] and [[main_contract_payment_schedule]]: the original Contract's Milestones and payment schedule, showing their current dates and amounts

See Contract Personalisations.

Example: adding one Milestone and changing another

  1. On the original Contract, edit the existing Milestone's due date and amount.

  2. Click Create Variation, and at the Milestones step add the new Milestone with Create Milestone.

  3. In the Variation document, summarise both changes.

  4. Send the Variation for signing.

Completing a Variation

A Contract Variation has its own independent status, separate from the original contract it was created from. Once a Variation's own milestones are all approved (or Finance Approved) or paid, it can be marked Complete the same way as any contract, via the Complete button in its Actions section.

Marking a Variation as Complete does not automatically mark the original contract as Complete, and completing the original doesn't affect any of its Variations — each is tracked independently. If you want both the original contract and the Variation to show as Completed, mark each one individually.

See Completing a Contract for more on how the Complete action works.

FAQs

Does the original Contract still exist after I create a Variation?

Yes. The original Contract, its signed document and its Milestones all stay in place. The Variation sits alongside it as a separate, linked Contract with its own document, Milestones and status.

Will editing a Milestone on the original Contract change its signed document?

No. A signed Contract document is a snapshot of what was agreed when it was signed, and it never changes. The Milestone itself is updated for tracking and payment, which is why the change should also be recorded in the Variation document.

Last updated

Was this helpful?