Creating a Contract Variation
Use a Contract Variation to formally amend a signed Contract, for example to add a Milestone or change a Milestone's date or amount.
A Contract Variation is a formal amendment to a signed Contract. It's a separate Contract that sits alongside the original, signed by both parties in its own right. The original Contract stays active and unchanged, and its Milestones carry on as they are.
This means a Variation only needs to contain what's changing, not a copy of the whole Contract.
What carries over from the original Contract
The linked Application (if any)
Title
Contract Category
Start and end dates
Contract Manager
Contract Amount
Bank account number
Milestones
Contract document and signatories
The Counterparty starts as the original Contract's Counterparty, but you can change it on the Variation, for example if the original organisation has handed the work on to someone else. See Creating a Contract.
The original Contract's Milestones are not copied into the Variation. They stay on the original Contract, where they continue to be tracked, submitted and paid as normal.
How to create a Variation
Open the original Contract
Go to Contracts, open the Contract you want to vary, and click Create Variation in the Actions section of the sidebar.
Create Variation only appears on an original Contract once it's fully executed (signed by your organisation). It isn't offered on a Variation, because a Variation can't be varied further. If you need to change a Variation, create another Variation against the original Contract.
Milestones
Add only the new Milestones that this Variation introduces, using Create Milestone or Import Template. You can also click Skip Milestones if the Variation doesn't add any.
You don't need to re-add the original Contract's Milestones. To change one of those, see Changing an existing Milestone below.
Changing an existing Milestone
To change the due date or amount of a Milestone that's already on the original Contract:
Edit the Milestone where it is, on the original Contract. Open it from the original Contract and update its Due date and Amount. This keeps tracking and payment correct, and avoids having two versions of the same Milestone.
Record the change in the Variation document, for example: "Milestone 2: due date changed from 31 March to 30 June; amount changed from $10,000 to $12,000."
Making the changes clear to the other party
Tahua doesn't highlight differences between the original Contract and the Variation, so it's best to spell them out. We recommend the Variation document includes a short summary of what's changed, such as Milestones added, dates or amounts changed, and any new terms.
If you'd also like the full picture in the document, these personalisations are available in your Contract template:
[[milestone_table]]: the Variation's own (new) Milestones[[main_contract_milestone_table]]and[[main_contract_payment_schedule]]: the original Contract's Milestones and payment schedule, showing their current dates and amounts
See Contract Personalisations.
Example: adding one Milestone and changing another
On the original Contract, edit the existing Milestone's due date and amount.
Click Create Variation, and at the Milestones step add the new Milestone with Create Milestone.
In the Variation document, summarise both changes.
Send the Variation for signing.
Completing a Variation
A Contract Variation has its own independent status, separate from the original contract it was created from. Once a Variation's own milestones are all approved (or Finance Approved) or paid, it can be marked Complete the same way as any contract, via the Complete button in its Actions section.
See Completing a Contract for more on how the Complete action works.
FAQs
Last updated
Was this helpful?